Planning/1.7: Difference between revisions
(Created page with 'This release will span a single quarter (3 months). We will have a 2.5 week freeze of the master branch. During this time, only bug fixes will be committed. == Release Schedul…') |
|||
Line 32: | Line 32: | ||
== Targeted Features == | == Targeted Features == | ||
[[Features/ACPITableGeneration]] | |||
[[Features/PCIBridgeHotplug]] | |||
See the [[ChangeLog/1.7]] for full details. | See the [[ChangeLog/1.7]] for full details. |
Revision as of 15:06, 10 September 2013
This release will span a single quarter (3 months). We will have a 2.5 week freeze of the master branch. During this time, only bug fixes will be committed.
Release Schedule
2013-08-15 | Beginning of 1.7 development phase |
2013-09-15 | Mid-point of development cycle |
2013-10-15 | Soft feature freeze. Major features should have initial code committed by this date. |
2013-10-29 | Hard feature freeze. Tag v1.7.0-rc0, only bug fixes committed after this point |
2013-11-01 | Tag v1.7.0-rc1 |
2013-11-07 | Tag v1.7.0-rc2 |
2013-11-13 | Tag v1.7.0-rc3 |
2013-11-15 | Tag v1.7.0 |
Known issues
Targeted Features