Planning/1.2: Difference between revisions
(Created page with 'This release will span a single quarter (3 months). We will have a 2.5 week freeze of the master branch. During this time, only bug fixes will be committed. == Release Schedul…') |
(Add some initial targeted features for the 1.2 soft freeze) |
||
Line 25: | Line 25: | ||
| Tag v1.2.0 | | Tag v1.2.0 | ||
|} | |} | ||
== Targeted Features == | |||
* MegaSAS - TODO: WWN | |||
* [[Features/QOM/CPU|QOM/CPU]] - CPU as a DeviceState? |
Revision as of 15:02, 31 July 2012
This release will span a single quarter (3 months). We will have a 2.5 week freeze of the master branch. During this time, only bug fixes will be committed.
Release Schedule
2011-06-01 | Beginning of 1.2 development phase |
2012-07-01 | Sprint 1 |
2012-08-01 | Soft feature freeze. Major features should have initial code committed by this date. |
2012-08-15 | Hard feature freeze. Tag v1.2.0-rc0, only bug fixes committed after this point |
2012-08-22 | Tag v1.2.0-rc1 |
2012-08-29 | Tag v1.2.0-rc2 |
2012-09-01 | Tag v1.2.0 |
Targeted Features
- MegaSAS - TODO: WWN
- QOM/CPU - CPU as a DeviceState?