This release will span a single quarter (3 months). We will have a 2.5 week freeze of the master branch. During this time, only bug fixes will be committed.

Release Schedule

2013-08-15 Beginning of 1.7 development phase
2013-09-15 Mid-point of development cycle
2013-10-15 Soft feature freeze. All features should have patches on the list by this date; major features should have initial code committed.
2013-10-29 Hard feature freeze. Tag v1.7.0-rc0, only bug fixes committed after this point
2013-11-01 Tag v1.7.0-rc1
2013-11-07 Tag v1.7.0-rc2
2013-11-13 Tag v1.7.0-rc3
2013-11-15 Tag v1.7.0

Known issues

Targeted Features

Features/ACPITableGeneration

Features/PCIBridgeHotplug