Planning/2.7
Release Schedule
2015-05-12 | Beginning of development phase |
2016-06-28 | Soft feature freeze. All features
should have patches on the list by this date; major features should have initial code committed. |
2016-07-19 | Hard feature freeze. Tag -rc0,
only bug fixes committed after this point |
2016-07-26 | Tag v2.7.0-rc1 |
2016-08-02 | Tag v2.7.0-rc2 |
2016-08-09 | Tag v2.7.0-rc3 |
2016-08-16 | Tag v2.7.0 |
Known issues
Please list all patch series or bugs which need to be fixed for the release here. That way I can be sure I don't miss any when I'm rolling release candidates.
Also see Planning/2.7/Testing.
Still unfixed in master
Targeted Features
See the ChangeLog/2.7 for full details.