Planning/2.1
Release Schedule
2013-04-17 | Beginning of 2.1 development phase |
2014-05-17 | Mid-point of development cycle |
2014-06-17 | Soft feature freeze. All features
should have patches on the list by this date; major features should have initial code committed. |
2014-07-01 | Hard feature freeze. Tag v2.1.0-rc0,
only bug fixes committed after this point |
2014-07-08 | Tag v2.1.0-rc1,
PCI/PC/VIRTIO/VHOST: only high priority fixes from here on. high priority means regression fixes or fixes in a new feature if there is no workaround. |
2014-07-15 | Tag v2.1.0-rc2 |
2014-07-22 | Tag v2.1.0-rc3 |
2014-07-29 | Tag v2.1.0 |
Known issues
Also see Planning/2.1/Testing.
Targeted Features
See the ChangeLog/2.1 for full details.