Planning/2.1
Release Schedule
2013-04-17 | Beginning of 2.1 development phase |
2014-05-17 | Mid-point of development cycle |
2014-06-17 | Soft feature freeze. All features
should have patches on the list by this date; major features should have initial code committed. |
2014-07-01 | Hard feature freeze. Tag v2.1.0-rc0,
only bug fixes committed after this point |
2014-07-08 | Tag v2.1.0-rc1,
PCI/PC/VIRTIO/VHOST: only high priority fixes from here on. high priority means regression fixes or fixes in a new feature if there is no workaround. |
2014-07-15 | Tag v2.1.0-rc2 |
2014-07-22 | Tag v2.1.0-rc3 |
Tag v2.1.0-rc5 (there was a bug found and fixed after tagging of -rc4 but before tarball creation so for practical purposes we skipped the rc4) | |
Tag v2.1.0 | |
Freeze for v2.1.1 | |
Tag v2.1.1 | |
2014-09-25 | Tag v2.1.2 (unplanned release) |
2015-01-14 | Freeze for v2.1.3 |
2014-01-21 | Tag v2.1.3 |
Known issues
- rc1 may fail a string output visitor test
Also see Planning/2.1/Testing.
Targeted Features
See the ChangeLog/2.1 for full details.