Planning/2.6
Release Schedule
2015-12-17 | Beginning of development phase |
2016-03-01 | Soft feature freeze. All features
should have patches on the list by this date; major features should have initial code committed. |
Hard feature freeze. Tag -rc0,
only bug fixes committed after this point | |
2016-04-05 | Tag v2.6.0-rc1 |
2016-04-12 | Tag v2.6.0-rc2 |
2016-04-19 | Tag v2.6.0-rc3 |
2016-04-26 | Tag v2.6.0 |
Known issues
Please list all patch series or bugs which need to be fixed for the release here. That way I can be sure I don't miss any when I'm rolling release candidates.
Also see Planning/2.6/Testing.
Still unfixed in master
Will be fixed in rc1
- Compile failures if libnfs is enabled
Targeted Features
See the ChangeLog/2.6 for full details.