Planning/4.2
Release Schedule
Draft schedule, not yet confirmed.
2019-08-16 | Beginning of development phase |
2019-10-29 | Soft feature freeze. Only bug fixes after this point. All feature changes must be already in a sub maintainer tree and all pull requests from submaintainers must have been sent to the list by this date. |
Hard feature freeze. Tag rc0 | |
2019-11-12 | Tag rc1 |
2019-11-19 | Tag rc2 |
2019-11-26 | Tag rc3 |
2019-12-03 | Release; or tag rc4 if needed |
2019-12-10 | Release, if we needed an rc4 |
Known issues
Please list all patch series or bugs which need to be fixed for the release here. That way I can be sure I don't miss any when I'm rolling release candidates.
Fixed in rc1:
- linux-user static builds fail with glibc git master due to removed "stime" function https://bugs.launchpad.net/qemu/+bug/1852115
Not yet fixed in any rc:
Targeted Features
See the ChangeLog/4.2 for full details.