This release will span a single quarter (3 months). We will have a 2.5 week freeze of the master branch. During this time, only bug fixes will be committed.

Release Schedule

2013-05-20 Beginning of 1.6 development phase
2013-06-15 Mid-point of development cycle
2013-07-15 Soft feature freeze. Major features should have initial code committed by this date.
2013-07-29 Hard feature freeze. Tag v1.6.0-rc0, only bug fixes committed after this point
2013-08-01 Tag v1.6.0-rc1
2013-08-07 Tag v1.6.0-rc3
2013-08-12 Tag v1.6.0-rc3
2013-08-15 Tag v1.6.0

Known issues

Targeted Features

See the ChangeLog/1.6 for full details.