Release Schedule

2014-07-29 Beginning of development phase
2014-09-03 Mid-point of development cycle
2014-10-01 Soft feature freeze. All features

should have patches on the list by this date; major features should have initial code committed.

2014-11-04 2014-11-05 Hard feature freeze. Tag -rc0,

only bug fixes committed after this point

2014-11-11 Tag v2.2.0-rc1
2014-11-18 Tag v2.2.0-rc2
2014-11-25 Tag v2.2.0-rc3
2014-11-28 Tag v2.2.0-rc4
2014-12-04 Tag v2.2.0-rc5
2014-12-03 2014-12-05 2014-12-09 Tag v2.2.0
2015-03-05 Freeze for v2.2.1
2014-03-10 Tag v2.2.1

Targeted Features

See the ChangeLog/2.2 for full details.