Planning/2.12: Difference between revisions

From QEMU
(Created page with "== Release Schedule == Tentatively proposed dates, still to be discussed/agreed. {| border="1" | 2017-12-13 | Beginning of development phase |- | 2017-10-31 | Planning/Sof...")
 
Line 7: Line 7:
| Beginning of development phase
| Beginning of development phase
|-
|-
| 2017-10-31
| 2018-03-13
| [[Planning/SoftFeatureFreeze|Soft feature freeze]].  Only bug fixes after this point. All feature changes must be already in a sub maintainer tree and all pull requests from submaintainers must have been sent to the list by this date.
| [[Planning/SoftFeatureFreeze|Soft feature freeze]].  Only bug fixes after this point. All feature changes must be already in a sub maintainer tree and all pull requests from submaintainers must have been sent to the list by this date.
|-
|-

Revision as of 16:18, 30 January 2018

Release Schedule

Tentatively proposed dates, still to be discussed/agreed.

2017-12-13 Beginning of development phase
2018-03-13 Soft feature freeze. Only bug fixes after this point. All feature changes must be already in a sub maintainer tree and all pull requests from submaintainers must have been sent to the list by this date.
2018-03-20 Hard feature freeze. Tag rc0
2018-03-27 Tag rc1
2018-04-03 Tag rc2
2018-04-10 Tag rc3
2018-04-17 Release, or tag rc4 if extra RC cycle needed
2018-04-24 Release, if we needed an rc4.

Known issues

Please list all patch series or bugs which need to be fixed for the release here. That way I can be sure I don't miss any when I'm rolling release candidates.

Fixed in rc0

Not yet fixed in any rc

Issues that will not be fixed

Targeted Features

See the ChangeLog/2.12 for full details.