Planning/4.0

From QEMU

Release Schedule

Tentatively proposed dates, still to be discussed/agreed.

2018-12-12 Beginning of development phase
2019-03-12 Soft feature freeze. Only bug fixes after this point. All feature changes must be already in a sub maintainer tree and all pull requests from submaintainers must have been sent to the list by this date.
2019-03-19 Hard feature freeze. Tag rc0
2019-03-26 Tag rc1
2019-04-02 Tag rc2
2019-04-09 Tag rc3
2019-04-16 Release, or tag rc4 if extra RC cycle needed
2019-04-23 Release, if we needed an rc4.

Known issues

Please list all patch series or bugs which need to be fixed for the release here. That way I can be sure I don't miss any when I'm rolling release candidates.

Fixed in rc0

Fixed in rc1

Fixed in rc2

Fixed in rc3

Fixed in rc4

Not yet fixed in any rc

Issues that will not be fixed

Targeted Features

See the ChangeLog/4.0 for full details.