Planning/1.4
This release will span a single quarter (3 months). We will have a 2.5 week freeze of the master branch. During this time, only bug fixes will be committed.
Release Schedule
2012-12-03 | Beginning of 1.4 development phase |
2013-01-15 | Soft feature freeze. Major features should have initial code committed by this date. |
2013-02-01 | Hard feature freeze. Tag v1.3.0-rc0, only bug fixes committed after this point |
2013-02-04 | Tag v1.3.0-rc1 |
2013-02-08 | Tag v1.3.0-rc2 |
2013-02-15 | Tag v1.3.0 |
Known issues
Targeted Features
See the ChangeLog/1.4 for full details.