Planning/2.5
Release Schedule
To be decided, but probably release early to mid December.
2015-08-11 | Beginning of development phase |
2015-??-?? | Soft feature freeze. All features
should have patches on the list by this date; major features should have initial code committed. |
2015-??-?? | Hard feature freeze. Tag -rc0,
only bug fixes committed after this point |
2015-??-?? | Tag v2.4.0-rc1 |
2015-??-?? | Tag v2.4.0-rc2 |
2015-??-?? | Tag v2.4.0-rc3 |
2015-??-?? | Tag v2.4.0-rc4 |
2015-??-?? | Tag v2.4.0 |
Known issues
Please list all patch series or bugs which need to be fixed for the release here. That way I can be sure I don't miss any when I'm rolling release candidates.
Also see Planning/2.4/Testing.
Targeted Features
See the ChangeLog/2.4 for full details.