Planning/10.1
Release Schedule
2025-04-22 | Beginning of development phase |
2025-07-22 | Soft feature freeze. Only bug fixes after this point. All feature changes must be already in a sub maintainer tree and all pull requests from submaintainers must have been sent to the list by this date. |
2025-07-29 | Hard feature freeze. Tag rc0 |
2025-08-05 | Tag rc1 |
2025-08-12 | Tag rc2 |
2025-08-19 | Tag rc3 |
2025-08-26 | Release; or tag rc4 if needed |
2025-09-02 | Release if we needed an rc4 |
Known issues
Please use GitLab Issues to track release blocker bugs:
https://gitlab.com/qemu-project/qemu/-/milestones/16
Other release info
Feel free to add non-bug information that is pertinent to the release here.