Planning/2.6: Difference between revisions
(Removed postcopy bug; fixed by 864699227911909ef1e33ecf91bf3c900715a9b1) |
No edit summary |
||
Line 10: | Line 10: | ||
have initial code committed. | have initial code committed. | ||
|- | |- | ||
| 2016-03-29 | | <strike>2016-03-29</strike> 2016-03-30 | ||
| [[Planning/HardFeatureFreeze|Hard feature freeze]]. Tag -rc0, | | [[Planning/HardFeatureFreeze|Hard feature freeze]]. Tag -rc0, | ||
only bug fixes committed after this point | only bug fixes committed after this point |
Revision as of 19:11, 30 March 2016
Release Schedule
2015-12-17 | Beginning of development phase |
2016-03-01 | Soft feature freeze. All features
should have patches on the list by this date; major features should have initial code committed. |
Hard feature freeze. Tag -rc0,
only bug fixes committed after this point | |
2016-04-05 | Tag v2.6.0-rc1 |
2016-04-12 | Tag v2.6.0-rc2 |
2016-04-19 | Tag v2.6.0-rc3 |
2016-04-26 | Tag v2.6.0 |
Known issues
Please list all patch series or bugs which need to be fixed for the release here. That way I can be sure I don't miss any when I'm rolling release candidates.
Also see Planning/2.6/Testing.
Targeted Features
See the ChangeLog/2.6 for full details.