Release Schedule
2016-05-12 | Beginning of development phase |
2016-06-28 | Soft feature freeze. All features
should have patches on the list by this date; major features should have initial code committed. |
Hard feature freeze. Tag -rc0,
only bug fixes committed after this point | |
Tag v2.7.0-rc1 | |
Tag v2.7.0-rc2 | |
2016-08-09 | Tag v2.7.0-rc3 |
2016-08-16 | Tag v2.7.0 |
Known issues
Please list all patch series or bugs which need to be fixed for the release here. That way I can be sure I don't miss any when I'm rolling release candidates.
Also see Planning/2.7/Testing.
Still unfixed in master
Doesn't build on x86 OpenBSD or NetBSD. (Patch on list, should be fixed for rc3.)
Will be fixed in rc2
wxx: Truncate files used for character devices
Targeted Features